Philips Ambition X 1.5T: quench during second field ramp at installation

What happened

During a new site installation of a helium-free BlueSeal magnet, after warm vacuum and cooldown, a quench occurred on the second field ramp, at maximum current on the way to the set point. The third ramp completed and the system was brought to the end of commissioning.

What was checked

Cause

Not determined: the quench occurred at maximum current during the second ramp, and no root cause was named in the case.

What was done

After the quench, the engineers let the magnet re-cool (reported about 2.5 days) and then performed a third field ramp, which completed successfully; shimming, settings and final tests were finished afterwards. No parts were replaced.

Safety

During any field ramp keep all personnel out of the magnet room, confirm the quench vent is routed and clear and oxygen monitoring is working, and treat the cryocompressors as critical equipment — on this helium-free design their stop was reported to trigger a quench.

Lesson: First energisation of a helium-free magnet is not a routine ramp-up: plan reserve time for quench recovery, and never break the cryo cooling chain on platforms where a stop means a quench.