What the service budget covers, and why heads of department lose budget discussions

Describe every cost line of a medical equipment service budget, separate operating from capital spending, link the budget to the value of the inventory, and recognise the habits that make a budget easy to cut.

Why the budget meeting goes wrong

Most new heads of department meet the budget for the first time as a single number: last year's figure, with a percentage added for inflation, sent to finance in a spreadsheet nobody else understands. Finance then asks three questions. What does this money buy? What happens if we give you less? Why is it more than last year? If the answers are 'maintenance', 'things will break' and 'prices went up', the budget will be cut, and the cut will land wherever finance chooses rather than where the risk is lowest.

Finance is not hostile. Finance has to choose between your request and a dozen others, and it can only defend what it can see. A department that shows what it maintains, how, with whom, at what cost per device and with what result is giving finance an argument. A department that shows one number is asking for trust, and trust is the first thing to go when money is short.

This course is about turning the budget from a number into an argument. It assumes you already run, or are building, a planned maintenance programme as described in the first course of this line, Planned Maintenance Programme for Medical Equipment (pm-programme). The budget is the financial side of that programme: it pays for the inventory, the procedures, the schedule and the people, and it should be built from them.

Operating costs and capital costs

The first distinction finance will make is between operating and capital spending, and you need to make it before they do. WHO's Medical equipment maintenance programme overview (2011, section 4.3.1) divides the money a maintenance programme needs into initial costs, paid before the programme starts, and operating costs, paid every year to keep it running. It groups both into physical resources (space, tools, test equipment, computers, vehicles and their upkeep), human resources (recruitment and initial training, then salaries, benefits, staff turnover and continuing education) and direct maintenance (service contracts, parts and materials, travel and shipping).

In hospital finance the same idea usually appears as an operating budget and a capital budget. The operating budget pays for the year: salaries, contracts, parts, calibration, training, software subscriptions. The capital budget pays for assets that last several years: new and replacement medical equipment, a new analyser for the workshop, a CMMS purchase, a workshop fit-out. The line between them is set by your hospital's accounting policy and national rules, usually by a value threshold and an expected life. An item of test equipment may be capital in one hospital and an operating expense in another. Ask your finance department for the threshold and the account codes before you build anything, and use their categories, not your own.

Keep the two budgets apart in your own head too. Replacing a ventilator is a capital decision; keeping it running until then is an operating cost. Lesson 5 covers replacement planning and the capital side. Lessons 2 to 4 and 6 are mainly about the operating budget, which is where most departments lose their arguments.

The lines of an operating service budget

Whatever the size of the hospital, the operating budget of a service department is made of the same lines. Some departments see only part of the picture because other lines sit in other budgets: contracts in a procurement budget, parts bought by clinical departments, salaries in a central HR budget. For your own analysis, collect all of them, even if you only control some.

Two lines deserve a warning. Software is rarely just the licence: WHO's Computerized maintenance management system guide (2011, section 4.2.1) lists hidden charges to take into account, such as annual licence fees, extra data storage, upgrades and technical support. And test equipment is not a one-off purchase: WHO's overview says ongoing funding is needed to buy, calibrate and service test equipment as new medical equipment arrives.

  • Staff: salaries, employer contributions and benefits, overtime and on-call payments, recruitment.
  • Service contracts: full-service, PM-only or shared-responsibility agreements with manufacturers or independent service companies.
  • Time-and-materials repairs: external engineer hours, travel and parts charged per job.
  • Parts and materials: PM kits, batteries, filters, wear parts, repair parts bought by your own department.
  • Test equipment and calibration: calibration of analysers, repair of test equipment, and a provision to replace it.
  • Tools and workshop: hand tools, consumable materials, workshop utilities and upkeep.
  • Training: manufacturer and independent technical courses, travel to training, competency records.
  • Software: CMMS licence or subscription, support, data storage, service software where its use is licensed to you.
  • Travel and shipping: travel between sites, shipping of parts and equipment sent away for repair.

Linking the budget to the value of the inventory

A budget becomes easier to defend when it is tied to something management already values. The obvious anchor is the equipment itself. WHO's inventory guide (Introduction to medical equipment inventory management, 2011, section 9.1) describes the inventory as the basis for forecasting budgets: annual service and operating costs are planned from it, and capital budgets are forecast from current values, expected lifetimes and the equipment that needs replacing. If your inventory does not record the purchase cost of each device, that is the first gap to close (lesson 2).

WHO's overview defines a measure that links the two directly, the cost of service ratio: the total annual cost of operating the maintenance programme divided by the initial cost of the medical equipment in the inventory. WHO quotes a range of 5% to 10% for the United States, citing an AAMI benchmarking analysis (Cohen, 2010). WHO adds two cautions. That level is reached only with substantial supporting resources and after a long period of improvement, and new programmes in resource-constrained settings may be much higher. And the ratio should be monitored over time as a guide to improvement. It is not a target, and it is not a reason to cut maintenance that the manufacturer requires.

Use the ratio for three things. First, as a trend for your own department from year to year. Second, to compare categories of equipment inside your hospital, which shows where the money goes (lesson 2). Third, to explain scale to management: 'we spend this much each year to keep this much equipment safe and working' is a sentence finance understands.

Example: one hospital's budget on one page (invented sample numbers)

EXAMPLE ONLY. The figures below are invented to show the structure. They are not benchmarks for any hospital or country.

A fictional hospital has medical equipment with a total purchase value of $20,000,000 in its inventory. Its service department's operating costs last year, collected from all budgets, were:

Total: $1,600,000. The cost of service ratio is 1,600,000 / 20,000,000 = 8%. Notice what the page already tells management. Contracts and staff are 78% of the money ($1,250,000 of $1,600,000), so any serious discussion about cost is a discussion about service strategy and staffing (lessons 3 and 4), not about tools or travel. And the department can now say what a cut of, say, $100,000 would actually mean, line by line, instead of absorbing it blindly.

  • Service contracts: $650,000
  • Staff (6 engineers, 1 manager, employer costs included): $600,000
  • Parts and materials: $180,000
  • Time-and-materials repairs: $70,000
  • Test equipment calibration and replacement provision: $40,000
  • Training: $30,000
  • CMMS and software: $20,000
  • Travel and shipping: $10,000

Why heads of department lose budget discussions

The same patterns appear in hospital after hospital. You will probably recognise at least two in the budget you inherit.

None of these is solved by better presentation alone. Each is solved by data and structure, which the next lessons build: the numbers (lesson 2), the service strategy (lesson 3), the staff case (lesson 4), the replacement plan (lesson 5) and the budget itself with its monthly control (lesson 6). One rule runs through all of them: savings come from contracts, parts, scope, data, training and the timing of replacement. They never come from skipping maintenance the manufacturer requires or from keeping life-support equipment in service past safe limits. Where tax, depreciation or procurement rules matter, they differ by country; check them with your finance department.

  • One number, no structure: the budget is last year plus a percentage, and nobody can say what is inside it.
  • No link to the equipment: the budget is not tied to the inventory, so new equipment arrives and warranties end without any change to the money.
  • Costs scattered across budgets: contracts, parts and staff sit in different places, so the department cannot show the full cost or defend any part of it.
  • Engineering language: the request talks about PM kits and analyser calibration instead of risk, availability, compliance and money.
  • No consequences shown: management cannot see what a cut would remove, so the cut lands on the easiest line rather than the safest one.
  • No control during the year: overspending is discovered in the last quarter, when the only options left are bad ones.
Unit breakdownThe lines of a service budget
PartWhat it doesHow it fails
01StaffEngineers, technicians and manager, with employer costs.Held in a central HR budget, so the true cost is unknown.
02Service contractsExternal maintenance under a fixed annual price.Renewed automatically without checking scope or devices covered.
03Time-and-materials repairsExternal repairs paid per job.No reserve set, so one large repair breaks the budget.
04Parts and materialsPM kits, batteries, filters and repair parts.Bought by wards or projects, invisible to the department.
05Test equipment and calibrationCalibration, repair and planned replacement of analysers.Calibration forgotten until an audit; no replacement provision.
06TrainingTechnical courses and competency for the equipment you maintain.First line cut every year, then contracts grow to cover the gap.
07Software (CMMS)Records, scheduling, cost history and reports.Budgeted as a licence only, without support and storage fees.
08Travel and shippingTravel between sites and shipping of parts and units.Spread across many small invoices and never totalled.
Fault-finding flowIs your budget request ready for finance?
You are asked to submit nextyear's service budget.Does every cost linehave an amount and anowner budget?1NoCollect contracts, parts and staffcosts from all budgets first.YesIs the request splitinto operating andcapital?2NoGet finance's threshold and accountcodes; split the lines.YesIs it tied to theinventory and itspurchase value?3NoAdd purchase values to theinventory; calculate the cost ofservice ratio.YesAre changes from lastyear explained line byline?4NoList new equipment, endedwarranties, retirements and pricechanges.YesCan you show what a10% cut would remove?5NoPrepare scope options; never offerskipping required maintenance.YesSubmit the request with itsassumptions on one page(lesson 6).
Trainer: walk the fault-finding flowAnswer each check as if you were at the machine. The flow leads you to the cause.
field case

The budget that was cut by a flat 15%

A typical situation: a new head of a biomedical engineering department submits the service budget as last year's total plus 6%. The hospital is short of money and finance cuts every department's request by 15%. With no breakdown agreed in advance, the head absorbs the cut where it is easiest to stop paying: the training budget and two service contracts that are up for renewal, one of them for the anaesthesia machines. Within months the hospital is paying time-and-materials rates for anaesthesia repairs, and the engineers are not trained to take over the work. The next year the head builds the budget from the inventory, line by line, with the contracts listed by device and the consequence of each possible cut written next to it. Finance still asks for savings, but now they are chosen together, from contract scope and parts, and the anaesthesia contract is protected.

A budget without structure is cut where it is easiest, not where it is safest. Show the lines and the consequences before anyone asks.

From service practice

The contracts nobody counted

A typical situation: a department head believes the service budget is about $400,000 a year, because that is what her department controls. When she collects invoices from procurement, imaging and the laboratory, she finds another $350,000 of service contracts signed directly by those departments, several of them for equipment her engineers also maintain. Two contracts cover devices that were retired years ago. Her first budget proposal shows the full $750,000, the overlaps and the retired devices, and asks for all service contracts to pass through her department for technical review.

Find all the money before you defend any of it. Costs held in other budgets are still part of the cost of keeping equipment working.

On-site checklist

  • Collect every cost line, including contracts and parts held in other departments' budgets.
  • Ask finance for the capital threshold, account codes and budget calendar.
  • Split the request into operating and capital.
  • Check that the inventory records the purchase value of each device.
  • Calculate the cost of service ratio and treat it as your own trend, not a target.
  • Include hidden software costs: support, storage and upgrades.
  • Include a provision to calibrate and replace test equipment.
  • Explain every change from last year line by line.
  • Prepare the consequences of possible cuts in advance, without offering to skip required maintenance.

Check yourself

1. Finance asks why your service budget should not simply be cut by 10%. Which answer is most likely to protect the right things?
2. How does WHO define the cost of service ratio?
3. Your cost of service ratio is higher than the 5% to 10% range WHO quotes for the United States. What is the right conclusion?
4. A new electrical safety analyser costs more than your hospital's capital threshold. Where does it belong?
5. You are told the CMMS costs 'only the licence'. What else should the budget include, according to WHO's CMMS guide?