How to set up a planned maintenance programme for medical equipment
2026-11-21
A planned maintenance programme answers four questions for every device in a hospital: is it on the list, how often is it inspected, who does the work, and how do you know the work was done. This guide walks through the steps, based on two open WHO documents and the US CMS memorandum on alternate equipment maintenance.
Build the inventory first
You cannot plan maintenance for equipment you have not listed. WHO's *Introduction to medical equipment inventory management* (2011) lists the minimum data for each record:
- equipment identification number (your own tag);
- type of equipment, using a standard nomenclature such as GMDN or UMDNS;
- short description, manufacturer, model and serial number;
- physical location;
- operating status (in service, out of service and why);
- power requirements and special service requirements;
- maintenance service provider and contract details;
- purchase supplier, and the date the record was created or updated.
Useful additions include software and firmware version, purchase date and cost, warranty expiry, acceptance test results, the risk assessment, the maintenance schedule, calibration dates, service history and recalls. WHO also advises checking regularly that everything in use is in the inventory and everything in the inventory can be found, and adding new equipment at acceptance testing.
Decide what goes into the programme
Not every device needs scheduled maintenance. WHO's *Medical equipment maintenance programme overview* (2011) describes several ways to prioritise:
- risk-based: highest priority to equipment most likely to injure a patient if it fails;
- mission-based: equipment most important to the care your facility mainly provides;
- maintenance-based: devices that can harm a patient if they malfunction and are likely to malfunction without maintenance;
- resource-based: any of the above, adjusted to the staff and money you actually have.
WHO's appendix gives a sample risk-based method, a modified Fennigkoh and Smith model. Each device type gets an equipment management (EM) number:
| Factor | Range in the WHO sample |
|---|---|
| Equipment function (life support down to non-clinical) | 2 to 10 |
| Physical risk in clinical use (no risk up to potential patient death) | 1 to 5 |
| Maintenance requirement (visual check up to routine calibration and parts) | 1 to 5 |
| Incident history (insignificant to significant failures) | −2 to +2 |
In that sample, device types scoring 12 or more are included in scheduled maintenance; the rest can stay in the inventory on a repair-only basis. Treat the thresholds as WHO's example, not a rule: set and document your own.
Set the intervals
WHO's starting point is the manufacturer's recommended frequency. A manager may change what is inspected and how often once the team knows the equipment, considering regulations, the physical environment, user training, reliability, how often the device is used and how much wear it gets, and the staff available. WHO advises following the manufacturer when the team is not yet familiar with a device, and recording in the maintenance record any level set below the manufacturer's specification.
In the United States, CMS memorandum S&C 14-07-Hospital (20 December 2013) lets hospitals adjust maintenance frequency and activities from the manufacturer's recommendations through a documented Alternate Equipment Management (AEM) programme, based on a risk assessment by qualified personnel. The memo excludes:
- equipment for which other federal or state law, or other Conditions of Participation, require manufacturer maintenance, for example all imaging and radiologic equipment;
- medical laser devices;
- new equipment without enough maintenance history to support a risk-based decision.
Hospitals using AEM must identify critical equipment in the programme, follow the schedules they set, and evaluate the programme's effectiveness. Check the current CMS guidance and your national rules before changing any interval.
Build the schedule
WHO describes practical ways to schedule:
- inspect all equipment in one clinical department at the same time, which suits equipment that does not move;
- inspect all devices of one type together, for example all defibrillators;
- schedule by calendar from the manufacturer's recommendation, or by hours of use where that is the manufacturer's basis.
Spread the work over the year so it matches staff capacity, lighten it during holiday periods, and estimate the workload by multiplying the number of devices of each type by the time each inspection takes, plus preparation and documentation time. If the work cannot all be done, complete the highest-priority tier first rather than doing part of everything.
Report completion and measure the programme
WHO lists indicators a manager can track over time:
| Indicator | What it shows |
|---|---|
| Completion rate of scheduled inspections | Whether the plan is done; WHO suggests aiming above 90%, and higher for the highest-priority group |
| Equipment location rate | How accurate the inventory is |
| Inspection yield | Share of inspections that found a problem affecting operation or safety |
| Productivity | Actual time per inspection compared with expected time |
| Response time, repair time, downtime | How corrective maintenance performs |
| Mean time between failures, repeated failures | Reliability of devices and models |
The CMS memo similarly asks hospitals with an AEM programme to show how malfunctions are found and investigated, how unsafe equipment is removed from service, and how performance data is used to change the programme.
Keep the records that prove it
Each device needs a record of every scheduled and corrective job: what was done, when, by whom, the result and the next due date. These records also feed your staff competency file: who is trained to inspect which equipment. See our guide on documenting the competency of biomedical engineers.
Learn it step by step
The course Planned Maintenance Programme for Medical Equipment covers inventory, risk classification, intervals, scheduling and completion reporting with worked examples. For teams, see training for teams.
FAQ
Sources
- WHO. *Medical equipment maintenance programme overview*. WHO Medical device technical series, 2011.
- WHO. *Introduction to medical equipment inventory management*. WHO Medical device technical series, 2011.
- CMS. *S&C 14-07-Hospital: Hospital Equipment Maintenance Requirements*, 20 December 2013.
Do we have to follow the manufacturer's maintenance intervals?
Following them is the safe starting point. WHO allows a manager to adjust them with experience and a documented rationale. In the United States, the CMS AEM memo allows adjustment for many devices but not for imaging and radiologic equipment, medical lasers, or new equipment without maintenance history.
Does every device need preventive maintenance?
No. WHO describes risk-based selection: devices with low risk and no evidence of benefit from scheduled maintenance can stay in the inventory and be repaired when they fail.
What completion rate should we aim for?
WHO suggests a goal above 90% for scheduled inspections, with a higher goal for the highest-priority equipment.
What should a maintenance record contain?
The device identity, the work done, date, who did it, the result, and the next due date, plus time and cost if you track them.