01Lesson 1 / 6 · 20 min

What a planned maintenance programme is and why it matters

Explain to your team and to hospital management what a planned maintenance programme consists of, what it is for, who owns each part, and where your current arrangement is weakest.

A list of dates is not a programme

Most departments you will inherit already have something they call a PM plan. Usually it is a spreadsheet of devices with a due month, a box of stickers and a contractor who comes twice a year. That is a schedule. A programme is the system around it: a decision about what equipment is covered and why, a defined procedure for each type, a schedule that matches the people you actually have, records that prove the work, and a regular look at whether any of it is working.

The WHO document Medical equipment maintenance programme overview (2011) splits maintenance into two branches. The first is scheduled work, which WHO calls inspection and preventive maintenance (IPM). The second is corrective maintenance, that is repair after a failure. Inside the scheduled branch there are three different activities, and it helps to keep them apart in your head and in your paperwork:

WHO makes a point that every manager should repeat to their hospital: an inspection shows that the device was in good condition at the time it was checked. It does not promise that the device will not fail tomorrow, because electrical and mechanical parts can fail at any moment. A programme reduces failures and finds hidden ones; it does not abolish them. Corrective maintenance, user checks and a clear way to report faults are part of the same system.

  • Performance inspection: checking that the device does what the manufacturer says it should, against the limits in the service documentation. It tells you the condition today and does not extend the life of anything.
  • Safety inspection: checking that the device is electrically and mechanically safe for patient and operator, judged against the manufacturer and the applicable national or regional standards. Its frequency may be set by regulation rather than by the manufacturer.
  • Preventive maintenance in the narrow sense: work that extends life and prevents failure, such as cleaning filters, lubricating, replacing wear parts and parts with a finite life, and calibration.

What the programme is for

When you present the programme to management, talk about four goals. They pull against each other, and your job is to balance them openly rather than let one of them win by accident.

Safety comes first. A defibrillator whose battery can no longer deliver the required number of shocks, an infusion pump whose occlusion alarm no longer triggers, an anaesthesia machine with a leaking circuit: these faults are often invisible to the user until the moment they matter. Scheduled inspection exists to find them first.

Availability is the second goal. Equipment that is broken, missing or waiting for a part is not available for the patient who needs it. A programme that plans parts in advance, schedules work around clinical activity and repairs promptly keeps more equipment in use. Ward staff feel this goal more than any other.

Cost is the third. WHO describes a cost of service ratio: the total annual cost of running the maintenance programme divided by the purchase value of the equipment in the inventory. WHO quotes a range of 5 to 10 per cent for the United States, from AAMI benchmarking work, and warns that this level is reached only with substantial resources and years of improvement; new programmes in resource-limited settings will usually be higher. Use the ratio to follow your own trend, not to compare yourself with a different health system.

Compliance is the fourth. Accreditation bodies, regulators and tender committees will ask you to show what you maintain, how and with what result. In the United States, the CMS memorandum S&C 14-07-Hospital (20 December 2013) states that a hospital complies with the equipment maintenance requirement when it follows the manufacturer's recommended activities and schedule and keeps documentation of both the recommendations and the work done. Other countries have their own rules. Check your national regulation and accreditation standard before you decide what counts as compliant.

The six parts of a programme

Every working programme has the same six parts, whatever the size of the hospital. Each of the following lessons covers one or two of them in detail. If any part is missing, the others cannot do their job: a perfect schedule built on a wrong inventory sends engineers looking for equipment that is not there, and a good procedure without records cannot be proven to an auditor.

Notice that these parts form a loop. The review in part six changes the risk decisions, procedures and intervals in parts two to four, and the next year's schedule is built from the corrected version. A programme that never changes after its first year is either perfect or not being reviewed, and it is rarely perfect.

  • Inventory: every piece of equipment the department is responsible for, with a unique number, its identity, location, owner and status (lesson 2).
  • Risk-based inclusion: a documented decision for each equipment type about whether it gets scheduled maintenance, and how much priority (lesson 3).
  • Procedures and intervals: what is done at each PM for each type, how often, with which test equipment and against which limits (lesson 4).
  • Schedule and resources: the annual plan, the engineer-hours it needs, who does it (in-house staff or contractor) and how overdue work is handled (lesson 5).
  • Records: a record of every scheduled and corrective job that shows what was done, by whom, with what result and when it is next due (lesson 6).
  • Review: indicators such as completion rate and the share of inspections that find a problem, used to change the programme (lesson 6).

Who owns it

A programme needs one owner. In the WHO description that is the clinical engineering department, whatever its local name: biomedical engineering, medical equipment department, technical service. The department develops and keeps the inventory, selects what goes into the programme, writes or selects procedures, and reports results. Its manager, working with hospital administration, sets policies, proposes the budget, supervises technical staff, arranges training and sets priorities.

The CMS memo adds a point worth copying even outside the United States: hospital leadership assigns responsibility for equipment maintenance to named personnel, and the people who oversee the programme must be qualified. The hospital keeps records of the qualifications of its own staff and must be able to show how it makes sure contractors' staff are qualified too.

Ownership does not change when work is outsourced. A manufacturer or independent service company may do the PM of an MRI scanner or every dialysis machine in the hospital, but the hospital still owns the inventory record, the decision on intervals, the copy of the report and the follow-up when something fails. WHO is direct about this: when you use service contractors you need your own people to monitor and manage them.

Clinical staff are part of the programme too. They do pre-use and daily checks where the manufacturer requires them (WHO gives the daily test of a defibrillator as an example), report faults, tell you where equipment has gone, and release devices from use when PM is due. WHO also reminds engineers that after a PM the settings on a device may have been changed during testing, so users should check settings before connecting it to a patient again. Write that into your return-to-service routine.

For decisions that change risk, such as reducing the scope or frequency of maintenance on a device type, WHO suggests taking the evidence to a multidisciplinary safety committee or to hospital management, so that the decision is shared and recorded rather than taken alone by the engineering manager.

Where programmes usually break

When you take over a department, look for the common weak points before you change anything. The following are patterns seen again and again in hospital fleets; you will likely find at least two of them.

None of these is fixed by working harder. Each is fixed by one of the six parts above, and the rest of this course shows how.

  • The inventory is a purchasing list, not a list of what is on the wards. Devices bought on projects, donated, leased or brought in by doctors are missing; devices scrapped years ago are still scheduled.
  • Everything is scheduled and nothing is finished. The plan assumes more engineer-hours than exist, so the work done in a month depends on who shouted loudest, and some life-support equipment slips. WHO recommends the opposite: a tiered plan where the highest-priority group is completed first.
  • The procedure is the sticker. Engineers check that the device switches on, put a new date on it and move on, because no written procedure says what else to do.
  • Records show ticks but no values, so nobody can see a defibrillator's delivered energy or a pump's flow accuracy drifting over three years.
  • Contractor work is invisible. The contractor's report stays in the contractor's system, the hospital file says 'serviced', and nobody checks whether the visit covered every unit.
  • Nobody reviews. The same intervals have been used for ten years, and nobody can say whether PM on any type has ever found a fault.

How to use this course

By the end of lesson 6 you should have, for your own hospital or service contract, a short programme policy, a cleaned inventory with risk classification, a set of PM procedure sheets, an annual schedule with a staffing estimate, a record format and a quarterly report for management. You do not need software to start; WHO accepts that small facilities may run the programme on paper or a spreadsheet, and a computerised maintenance management system (CMMS) makes the larger ones manageable.

The course draws on two open WHO documents from the WHO Medical device technical series (2011) and on the CMS memorandum S&C 14-07-Hospital. WHO's material is guidance and offers sample methods to adapt. The CMS memo is a United States regulatory document and applies only to hospitals participating in Medicare and Medicaid; it is useful elsewhere as a clear description of what a regulator expects. The course is independent: it is not approved or endorsed by WHO, CMS, The Joint Commission or ISO. Paid standards such as ANSI/AAMI EQ56 (recommended practice for a medical equipment management programme) and EQ89 are named only as further reading. Where your country's rules differ, they take precedence.

Unit breakdownThe documents of a PM programme
PartWhat it doesHow it fails
01Programme policyNames the owner, scope, responsibilities and how decisions on intervals are made.Missing, or written once and never signed by hospital leadership.
02Equipment inventoryEvery device covered, with unique ID, identity, location, owner and status.Copied from purchasing; misses leased, donated and loaned equipment.
03Risk classification recordPer equipment type: score or rationale for inclusion and priority.Done once for an audit and not updated when new types arrive.
04PM procedure sheetsSteps, test equipment, limits and interval per type or model.Generic one-page checklist used for every device.
05Annual schedule and workload estimateWhen each device is due and the engineer-hours the plan needs.Built from due dates only, without checking staff capacity.
06Work orders and PM recordsEvidence of each job: date, person, results with values, next due.Ticks without values; contractor reports not filed.
07Test equipment registerAnalysers and tools with calibration status and due dates.Analyser out of calibration while records are still signed.
08Contractor fileScope, response terms, qualifications and reports for each contract.Contract exists but nobody checks visits against the inventory.
09Periodic programme reportCompletion, location rate, PM findings and actions for management.Never produced, so the programme cannot defend its budget.
Fault-finding flowQuick check: do you have a programme or only a schedule?
You have just taken over adepartment and need to knowwhere to start.Is there a writtenpolicy naming theowner of theprogramme?1NoWrite a one-page policy; havehospital leadership sign theassignment.YesDoes a sample of wardequipment match theinventory?2NoStart with an inventory clean-up(lesson 2) before reschedulinganything.YesIs there a documentedrisk decision for eachequipment type?3NoClassify types and record why eachis in or out of scheduled PM (lesson3).YesDoes each type have awritten PM procedurewith limits?4NoBuild procedure sheets frommanufacturer documentation (lesson4).YesDoes the schedule fitthe engineer-hours youactually have?5NoEstimate workload and tier the planso priority work finishes (lesson5).YesCan you show lastquarter's completionrate by prioritygroup?6NoSet up records and a quarterlyindicator report (lesson 6).YesAll yes: move to review andimprovement; check intervalsagainst PM findings.
Trainer: walk the fault-finding flowAnswer each check as if you were at the machine. The flow leads you to the cause.
field case

The department that was always 'on schedule'

A typical situation: a new head of biomedical engineering at a 400-bed hospital is told that PM is 'up to date'. The spreadsheet shows every device with a green due date. She takes twenty device numbers at random from the ICU and the operating theatres and goes to find them. Six are not where the list says, two have been scrapped, and three infusion pumps on the ward are not in the list at all. The stickers on the monitors carry this year's date, but the files hold no measured values, and the defibrillator records do not mention delivered energy or battery tests. Nobody is hiding anything; the schedule simply became the programme, and the programme stopped being checked.

Before you defend or change a PM plan, test it against the floor. A green spreadsheet proves only that dates were entered; the inventory, procedures and records behind it are what make it a programme.

From service practice

The budget meeting without numbers

A typical situation: the finance director proposes cutting the biomedical engineering budget and moving all maintenance to the cheapest contractor. The department head argues that this is unsafe but has nothing to show: no completion rate, no count of faults found during PM, no downtime figures, no list of critical equipment. The decision is postponed only because the medical director objects. In the following quarter the department starts reporting completion by priority group and the share of PMs that found a fault affecting safety or function, and the next budget discussion is about which equipment needs what, not about opinions.

A programme that does not measure itself cannot defend itself. Plan the indicators from day one, even if the first figures are uncomfortable.

On-site checklist

  • Find or write the programme policy and confirm who in hospital leadership assigned responsibility.
  • Spot-check twenty inventory entries against the floor, and twenty floor devices against the inventory.
  • List the equipment types that have a written PM procedure and the ones that do not.
  • Ask for last year's PM records for three critical types (for example defibrillators, ventilators, infusion pumps) and check for measured values.
  • List every service contract and check whether the reports are in the hospital's own files.
  • Find out whether any indicator (completion rate, faults found at PM) has ever been reported to management.
  • Check which national rules and accreditation standards apply to your hospital's equipment maintenance.

Check yourself

1. A ward sister asks why her monitors need PM 'if they are working fine'. Which answer best reflects the purpose of scheduled inspection?
2. Your hospital outsources all imaging maintenance to the manufacturer. An auditor asks who is responsible for that equipment's maintenance programme. What is the correct position?
3. Which set lists the six parts of a PM programme as described in this lesson?
4. You plan 100% of the inventory every year, but your team completes about two-thirds, and some ventilators are overdue. What does WHO recommend instead?
5. Finance asks for a single figure to follow the cost of the programme over time. Which measure does WHO describe for this?